120779RESERVE NOTICE21/11/2024 10:38:55 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1730 hrs 26/11/2024 to 1830 hrs 26/11/2024.
The forecast capacity reserve requirement is 525 MW.
The minimum capacity reserve available is 356 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
120778RECLASSIFY CONTINGENCY21/11/2024 08:32:47 PM

Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Duration: 21/11/2024 20:32 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
120777RECLASSIFY CONTINGENCY21/11/2024 08:10:26 PM

Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line

Duration: 21/11/2024 20:10 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
120775RESERVE NOTICE21/11/2024 06:52:08 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 24/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs 24/11/2024 to 1800 hrs 24/11/2024.
The forecast capacity reserve requirement is 1315 MW.
The minimum capacity reserve available is 1219 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120768PRICES SUBJECT TO REVIEW21/11/2024 06:10:22 PM

[EventId:202411211815_review] Prices for interval 21-Nov-2024 18:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1810 hrs on 21 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 21-Nov-2024 18:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120767PRICES SUBJECT TO REVIEW21/11/2024 06:06:35 PM

[EventId:202411211810_review] Prices for interval 21-Nov-2024 18:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 21 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 21-Nov-2024 18:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120765PRICES SUBJECT TO REVIEW21/11/2024 06:00:20 PM

[EventId:202411211805_review] Prices for interval 21-Nov-2024 18:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 21 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 21-Nov-2024 18:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120764PRICES SUBJECT TO REVIEW21/11/2024 05:55:14 PM

[EventId:202411211800_review] Prices for interval 21-Nov-2024 18:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 21 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 21-Nov-2024 18:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120763PRICES SUBJECT TO REVIEW21/11/2024 05:50:20 PM

[EventId:202411211755_review] Prices for interval 21-Nov-2024 17:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1750 hrs on 21 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 21-Nov-2024 17:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm