Update - Non-credible contingency event - VIC region - 12/11/2024
Update - Non-credible contingency event - VIC region - 12/11/2024
Refer AEMO Electricity Market Notice 120305
At 1135 hrs the Yallourn No 1 220 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 12/11/2024
Non-credible contingency event - VIC region - 12/11/2024
At 1041 hrs the Yallourn No 1 220 kV bus and Yallourn Unit 4 tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Cancellation - Forecast Minimum System Load 1 (MSL1) condition in the VIC Region on 10/11/2024
Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 07/11/2024.
Refer to Market Notice 119996 for Forecast MSL1.
AEMO Operations
Forecast Minimum System Load 1 (MSL1) condition in the VIC region on 10/11/2024
Update to Market Notice 119920 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1745 MW
o MSL2 - 1245 MW
o MSL3 - 745 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 1230 hrs to 1330 hrs 10/11/2024. Minimum regional demand is forecast to be 1719 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Cancellation - Forecast Minimum System Load 1 (MSL1) condition in the VIC Region on 09/11/2024
Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 06/11/2024.
Refer to Market Notice 119866 for Forecast MSL1.
AEMO Operations
Forecast Minimum System Load MSL1 condition in the VIC region on 10/11/2024
Update to Market Notice 119867 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1760 MW
o MSL2 - 1260 MW
o MSL3 - 760 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1000 hrs to 1430 hrs 10/11/2024. Minimum regional demand is forecast to be 1349 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Cancellation - Forecast Minimum System Load MSL1 condition in the VIC Region on 05/11/2024
Cancellation - Forecast Minimum System Load MSL1 condition in the VIC Region from 1200 hrs 05/11/2024.
Refer to Market Notice 119863.
Manager NEM Real Time Operations
Cancellation - Forecast Minimum System Load 2 (MSL2) in the VIC Region on 10/11/2024
Cancellation - Forecast MSL2, VIC Region at 0700 hrs 05/11/2024.
Refer to Market Notice 119852 for Forecast MSL2.
AEMO Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 10/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1735 MW
- MSL2 - 1235 MW
- MSL3 - 735 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 0930 hrs to 1230 hrs 10/11/2024. Minimum regional demand is forecast to be 1262 MW at 1230 hrs.
2. From 1300 hrs to 1500 hrs 10/11/2024. Minimum regional demand is forecast to be 1249 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO is seeking a market response.
AEMO Operations