CHG0100220 | Pre-Production | Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages
Change Start Date & Time: 09/12/2024 08:00:00 AEST
Change End Date & Time: 10/12/2024 23:00:00 AEST
Outage Start Date & Time: 09/12/2024 08:00:00 AEST
Outage End Date & Time: 10/12/2024 23:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: This Maintenance activity may cause intermittent outages to below applications during the outage period .
Impacted Systems:
1.EMMS systems (Dispatch/ PASA/ Forecasting/ Settlements)
2.Identity Service will be running only for authentication purposes.
3.Web Portal including menu items (Markets, Internal & Public portal)
4.GSH
5.GBB
6.Any GAS systems that have a NEMA / WARA database connection.
7.MSATS
8.CDR
9.DERR
If any ongoing issues are identified, please contact the AEMO Support Hub 1300 236 600.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Cancellation of Actual (LOR1) condition in the NSW region - 02/12/2024
Cancellation of Actual (LOR1) condition in the NSW region - 02/12/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121384 is cancelled at 1920 hrs 02/12/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/12/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/12/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1066 MW
Manager NEM Real Time Operations
INC0138848 - ALERT - EMMS - RESOLVED
The service interruption relating to the Electricity Market Management System service has been resolved.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
INC0138848 - ALERT - EMMS
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to the Electricity Market Management System service.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
STPASA - Update of the suspect Lack Of Reserve Level 3 (LOR3) condition in the NSW Region on 06/12/2024
The suspect LOR3 condition advised in AEMO Electricity Market Notice No. 121292 has been reviewed.
AEMO considers this forecast LOR3 condition invalid. Subsequent STPASA runs are producing valid solutions.
AEMO Operations
STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the NSW Region on 06/12/2024
AEMO considers that there is a suspect Forecast LOR3 condition for the NSW region for the following period:
From 1630 hrs 06/12/2024 to 1700 hrs 06/12/2024.
AEMO is currently investigating this LOR3 forecast condition to confirm whether they are valid.
AEMO Operations
Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121262 is cancelled at 1815 hrs 29/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1301 MW
Manager NEM Real Time Operations