Filter by category
Filter by Date
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1430 hrs 10/12/2024 to 1500 hrs 10/12/2024.
The forecast capacity reserve requirement is 810 MW.
The minimum capacity reserve available is 738 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 9 December 2024
NON-CONFORMANCE NSW1 Region Monday, 9 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 09/12/2024 00:40 to 09/12/2024 01:05
Amount: 7 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 9 December 2024
NON-CONFORMANCE NSW1 Region Sunday, 8 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 08/12/2024 23:50 to 09/12/2024 00:10
Amount: 6 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/12/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 121647 is cancelled at 2330 hrs 08/12/2024.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1430 hrs 10/12/2024 to 1500 hrs 10/12/2024.
The forecast capacity reserve requirement is 819 MW.
The minimum capacity reserve available is 802 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
NON-CONFORMANCE Region QLD1 Saturday, 7 December 2024
NON-CONFORMANCE QLD1 Region Saturday, 7 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 07/12/2024 18:45 to 07/12/2024 18:50
Amount: -12 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 7 December 2024
NON-CONFORMANCE NSW1 Region Saturday, 7 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 07/12/2024 03:30 to 07/12/2024 03:40
Amount: -6 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 06/12/2024
Network Augmentation Commissioned - NSW Region - 06/12/2024
At 1358 hrs 06/12/2024, the Buronga No.8 330/220 kV transformer has been commissioned.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 6 December 2024
NON-CONFORMANCE NSW1 Region Friday, 6 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 06/12/2024 09:10 to 06/12/2024 09:35
Amount: -45 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations