121528SETTLEMENTS RESIDUE06/12/2024 03:56:39 PM

[EventId:202412061555_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 06 December 2024 15:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1555 hrs on 6 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 December 2024.

Refer to market notice: 121510

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1555 hrs on 6 December 2024.

This is an AEMO autogenerated Market Notice.
     
121523MARKET INTERVENTION06/12/2024 03:50:18 PM

Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0700 hrs 07/12/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1615 hrs 06/12/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
121513PRICES SUBJECT TO REVIEW06/12/2024 02:45:17 PM

[EventId:202412061450_review] Prices for interval 06-Dec-2024 14:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1445 hrs on 6 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Dec-2024 14:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121512PRICES SUBJECT TO REVIEW06/12/2024 02:40:21 PM

[EventId:202412061445_review] Prices for interval 06-Dec-2024 14:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1440 hrs on 6 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Dec-2024 14:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121510SETTLEMENTS RESIDUE06/12/2024 02:36:40 PM

[EventId:202412061435_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 06 December 2024 14:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 6 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1435 hrs on 6 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121509PRICES SUBJECT TO REVIEW06/12/2024 02:35:24 PM

[EventId:202412061440_review] Prices for interval 06-Dec-2024 14:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 6 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Dec-2024 14:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121507PRICES SUBJECT TO REVIEW06/12/2024 02:30:16 PM

[EventId:202412061435_review] Prices for interval 06-Dec-2024 14:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1430 hrs on 6 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Dec-2024 14:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121506PRICES SUBJECT TO REVIEW06/12/2024 02:25:15 PM

[EventId:202412061430_review] Prices for interval 06-Dec-2024 14:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1425 hrs on 6 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Dec-2024 14:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121505PRICES SUBJECT TO REVIEW06/12/2024 02:20:18 PM

[EventId:202412061425_review] Prices for interval 06-Dec-2024 14:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1420 hrs on 6 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Dec-2024 14:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     