Filter by category
Filter by Date
[EventId:202411201400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 20 November 2024 14:00
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 20 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 November 2024.
Refer to market notice: 120709
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 20 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411201240_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 20 November 2024 12:40
Issued by Australian Energy Market Operator Ltd at 1240 hrs on 20 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1240 hrs on 20 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Project Energy Connect (PEC-1) testing 21st November 2024 0600-0900 for flows in both directions
Refer to market notice 120307
There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 21st November from 06:00hrs to 09:00hrs
This test includes includes a fast runback of Murraylink.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
Request for Generator Recall Information for the period from 25/11/2024 to 26/11/2024 for NSW Region
Refer to AEMO Electricity Market Notice no. 120700, 120699 and 120698.
Please provide Generator Recall Information for the period from 25/11/2024 to 26/11/2024, by 1200 hrs on 21/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
[EventId:202411192040_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 19 November 2024 20:40
Issued by Australian Energy Market Operator Ltd at 2040 hrs on 19 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 November 2024.
Refer to market notice: 120687
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2040 hrs on 19 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411191800_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 19 November 2024 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 19 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1800 hrs on 19 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411191750_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 19 November 2024 17:50
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 19 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 November 2024.
Refer to market notice: 120681
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1750 hrs on 19 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411191635_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 19 November 2024 16:35
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 19 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1635 hrs on 19 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120614 has been updated at 1400 hrs 19/11/2024 to the following:
1. From 1400 hrs to 1600 hrs 25/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1930 hrs to 2030 hrs 25/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 927 MW.
AEMO Operations