PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121069 has been updated at 1530 hrs to the following:
[1.] From 1430 hrs 28/11/2024 to 1930 hrs 28/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1108 MW.
Manager NEM Real Time Operations
AEMO Intervention Event - Intervention price dispatch intervals - dd/mm/yyyy
AEMO Intervention Event - Intervention price dispatch intervals - dd/mm/yyyy
Refer AEMO Electricity Market Notice no. 121100
An AEMO Intervention Event, the dispatch of Reliability and Emergency Reserve Trader (RERT) has been implemented.
The AEMO Intervention Event commenced at 15:45 hrs 27/11/2024 and is forecast to apply until 18:00 hrs 27/11/2024
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.
The AEMO Intervention Event is expected to affect dispatch quantities for intervention pricing purposes from the 15:50 hrs dispatch interval on 27/11/2024
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.
The Actual LOR2 condition is forecast to exist until 1700 hrs.
The capacity reserve required is 685 MW
The minimum reserve available is 412 MW
AEMO is seeking an immediate market response.
Manager NEM Real Time Operations
RERT DISPATCHED
AEMO Intervention Event, Reliability and Emergency Reserve Trader (RERT) - NSW1 Region- 27/11/2024
Refer AEMO Electricity Market Notice no. 121054
AEMO has dispatched/activated reserve contract(s) to maintain the power system in a Reliable operating state.
The reserve contract(s) was dispatched/activated at 15:45 hrs 27/11/2024 and is forecast to apply until 18:00 hrs 27/11/2024
AEMO has implemented an AEMO intervention event for the duration the reserve contract(s) is dispatched/activated/
To facilitate the RERT process, constraints commencing with the following identifiers may be evident at various times in dispatch,
#RT_NSW1
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 121048
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 27/11/2024.
The direction update is issued at 1620 hrs 27/11/2024.
Manager NEM Real Time Operations
STPASA - Cancellation of Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120955 is cancelled at 1400 hrs 27/11/2024.
AEMO Operations
Direction - SA region 27/11/2024
Direction - SA region 27/11/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 27/11/2024.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 121074
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 27/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 28/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 28/11/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 121074
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 27/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 28/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1430 hrs 28/11/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations