Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV
Duration: 20/11/2024 12:18 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Project Energy Connect (PEC-1) testing 21st November 2024 0600-0900 for flows in both directions
Refer to market notice 120307
There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 21st November from 06:00hrs to 09:00hrs
This test includes includes a fast runback of Murraylink.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
Request for Generator Recall Information for the period from 25/11/2024 to 26/11/2024 for NSW Region
Refer to AEMO Electricity Market Notice no. 120700, 120699 and 120698.
Please provide Generator Recall Information for the period from 25/11/2024 to 26/11/2024, by 1200 hrs on 21/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
INC0138395 - P1 - Electricity Market Management System service- RESOLVED
This incident has been uplifted to a P1.
The service interruption relating to the Electricity Market Management System service has been resolved.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120614 has been updated at 1400 hrs 19/11/2024 to the following:
1. From 1400 hrs to 1600 hrs 25/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1930 hrs to 2030 hrs 25/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 927 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 2000 hrs 26/11/2024.
The forecast capacity reserve requirement is 1347 MW.
The minimum capacity reserve available is 833 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
1. From 1230 hrs to 1430 hrs 26/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 891 MW.
2. From 2030 hrs to 2330 hrs 26/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1730 hrs to 1900 hrs 24/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1259 MW.
AEMO Operations
INC0138395 - Electricity Market Management System service- RESOLVED
The service interruption relating to the Electricity Market Management System service has been resolved.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager