Market Notices

118410RESERVE NOTICE23/09/2024 10:26:36 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118409 is cancelled at 2215 hrs 23/09/2024.

Manager NEM Real Time Operations
     
118409RESERVE NOTICE23/09/2024 05:21:24 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

From 1900 hrs 24/09/2024 to 1930 hrs 24/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 335 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
118407RESERVE NOTICE23/09/2024 03:51:29 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118401 is cancelled at 1550 hrs 23/09/2024.

Manager NEM Real Time Operations
     
118406MARKET SYSTEMS23/09/2024 03:44:02 PM

CHG0098666 | Production | Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098666

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Cisco IP Phone

Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Start Date & Time: 08/09/2024 00:00:00 AEST

Change End Date & Time: 08/09/2024 06:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: Outage Duration:
3 x 15 Minutes

Impacts:

Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .




     
118405MARKET SYSTEMS23/09/2024 03:36:16 PM

CHG0098660 | Production | Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098660

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Cisco IP Phone

Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Start Date & Time: 24/09/2024 00:00:00 AEST

Change End Date & Time: 24/09/2024 06:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: Outage Duration:
1 x 3 Hours

Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .

     
118401RESERVE NOTICE23/09/2024 01:26:46 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118396 has been updated at 1315 hrs to the following:

From 1930 hrs 23/09/2024 to 2100 hrs 23/09/2024.
The forecast capacity reserve requirement is 537 MW.
The minimum capacity reserve available is 443 MW.




Manager NEM Real Time Operations
     
118399RESERVE NOTICE23/09/2024 01:02:35 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

From 1730 hrs 24/09/2024 to 2130 hrs 24/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 382 MW.


Manager NEM Real Time Operations
     
118396RESERVE NOTICE23/09/2024 12:24:36 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118395 has been updated at 1220 hrs to the following:

From 2000 hrs 23/09/2024 to 2030 hrs 23/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 552 MW.




Manager NEM Real Time Operations
     
118395RESERVE NOTICE23/09/2024 10:19:53 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118392 has been updated at 1020 hrs to the following:

From 1830 hrs 23/09/2024 to 2200 hrs 23/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 450 MW.


Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm