121102MARKET INTERVENTION27/11/2024 03:47:01 PM

AEMO Intervention Event - Intervention price dispatch intervals - dd/mm/yyyy

AEMO ELECTRICITY MARKET NOTICE.

AEMO Intervention Event - Intervention price dispatch intervals - dd/mm/yyyy

Refer AEMO Electricity Market Notice no. 121100
An AEMO Intervention Event, the dispatch of Reliability and Emergency Reserve Trader (RERT) has been implemented.
The AEMO Intervention Event commenced at 15:45 hrs 27/11/2024 and is forecast to apply until 18:00 hrs 27/11/2024
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.
The AEMO Intervention Event is expected to affect dispatch quantities for intervention pricing purposes from the 15:50 hrs dispatch interval on 27/11/2024


Manager NEM Real Time Operations
     
121101RESERVE NOTICE27/11/2024 03:48:50 PM

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.

The Actual LOR2 condition is forecast to exist until 1700 hrs.
The capacity reserve required is 685 MW
The minimum reserve available is 412 MW

AEMO is seeking an immediate market response.

Manager NEM Real Time Operations
     
121100MARKET INTERVENTION27/11/2024 03:42:47 PM

RERT DISPATCHED

AEMO ELECTRICITY MARKET NOTICE.

AEMO Intervention Event, Reliability and Emergency Reserve Trader (RERT) - NSW1 Region- 27/11/2024

Refer AEMO Electricity Market Notice no. 121054
AEMO has dispatched/activated reserve contract(s) to maintain the power system in a Reliable operating state.
The reserve contract(s) was dispatched/activated at 15:45 hrs 27/11/2024 and is forecast to apply until 18:00 hrs 27/11/2024
AEMO has implemented an AEMO intervention event for the duration the reserve contract(s) is dispatched/activated/
To facilitate the RERT process, constraints commencing with the following identifiers may be evident at various times in dispatch,

#RT_NSW1


Manager NEM Real Time Operations
     
121094MARKET INTERVENTION27/11/2024 04:00:11 PM

Direction - SA region 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 27/11/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 27/11/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
121091MARKET INTERVENTION27/11/2024 03:59:01 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 121074


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 27/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 28/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 28/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
121090MARKET INTERVENTION27/11/2024 03:57:50 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 121074


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 27/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 28/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1430 hrs 28/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
121083MARKET INTERVENTION27/11/2024 02:18:44 PM

Direction - NSW region to Munmorah Battery ProjectCo Pty Ltd - WARATAHBESS1

AEMO ELECTRICITY MARKET NOTICE

Direction - NSW region to Munmorah Battery ProjectCo Pty Ltd - WARATAHBESS1

Refer to Market Notice 121070


In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to Munmorah Battery ProjectCo Pty Ltd. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Munmorah Battery ProjectCo Pty Ltd - WARATAHBESS1 at 1415 hrs 27/11/2024
Type of resource: bi-directional unit
Required actions: Maintain 96 MWh Energy Storage Level and follow dispatch targets at 1500 hrs 27/11/2024
Services provided: Reserve
Circumstances necessitating the Direction: Reliability
Circumstances necessitating the Direction additional detail: intervention is required to maintain the reliability standard

Expected duration: 1900 hrs 27/11/2024.


Manager NEM Real Time Operations
     
121082RECLASSIFY CONTINGENCY27/11/2024 01:30:20 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 27/11/2024 13:30 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
121074MARKET INTERVENTION27/11/2024 02:10:56 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 121059

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 28/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 27/11/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     