Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 11/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 08/12/2024 to 1930 hrs 08/12/2024.
The forecast capacity reserve requirement is 990 MW.
The minimum capacity reserve available is 920 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 08/12/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_5667C22F from 1600 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 06/12/2024
Cancellation - AEMO Intervention Event - SA region 06/12/2024
Refer to Market Notice 121524
The AEMO Intervention Event and all associated directions are cancelled from 1630 hrs on 08/12/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 121593
Direction is cancelled from: 1630 hrs 08/12/2024
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Glenn Innes to Tenterfield 96R 132kV line- NSW region - 08/12/2024
Inter-regional transfer limit variation -Glenn Innes to Tenterfield 96R 132kV line - NSW region - 08/12/2024
At 0333 hrs 08/12/2024 there was an unplanned outage of Glenn Innes to Tenterfield 96R 132kV line.
The following constraint set(s) invoked at 0345 hrs 08/12/2024
N-96L_96R_CB4102
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121608 is cancelled at 2020 hrs 07/12/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1900 hrs 08/12/2024 to 1930 hrs 08/12/2024.
The forecast capacity reserve requirement is 1000 MW.
The minimum capacity reserve available is 944 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121588 is cancelled at 1415 hrs 07/12/2024.
Manager NEM Real Time Operations