Cancellation of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: VIC1
Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV
Cancellation time: 27/11/2024 21:14
Constraint set(s) revoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 121073
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202411271830_review] Prices for interval 27-Nov-2024 18:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 18:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411271825_review] Prices for interval 27-Nov-2024 18:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 18:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411271820_review] Prices for interval 27-Nov-2024 18:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 18:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411271815_review] Prices for interval 27-Nov-2024 18:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 18:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411271810_review] Prices for interval 27-Nov-2024 18:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 18:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411271805_review] Prices for interval 27-Nov-2024 18:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 18:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024
Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024
The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121101 is cancelled at 1645 hrs 27/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.
The Actual LOR2 condition is forecast to exist until 1700 hrs.
The capacity reserve required is 685 MW
The minimum reserve available is 412 MW
AEMO is seeking an immediate market response.
Manager NEM Real Time Operations