PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 03/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:
[1.] From 1330 hrs 03/12/2024 to 1400 hrs 03/12/2024.
The forecast capacity reserve requirement is 771 MW.
The minimum capacity reserve available is 741 MW.
[2.] From 1430 hrs 03/12/2024 to 1500 hrs 03/12/2024.
The forecast capacity reserve requirement is 809 MW.
The minimum capacity reserve available is 636 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202412030645_confirmed] Prices for interval 03-Dec-2024 06:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0705 hrs on 3 December 2024
PRICES ARE NOW CONFIRMED for trading interval 03-Dec-2024 06:45.
In accordance with Market Notice 121394 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412030705_confirmed] Prices for interval 03-Dec-2024 07:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0705 hrs on 3 December 2024
PRICES ARE NOW CONFIRMED for trading interval 03-Dec-2024 07:05.
In accordance with Market Notice 121398 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412030700_confirmed] Prices for interval 03-Dec-2024 07:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0705 hrs on 3 December 2024
PRICES ARE NOW CONFIRMED for trading interval 03-Dec-2024 07:00.
In accordance with Market Notice 121397 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412030655_confirmed] Prices for interval 03-Dec-2024 06:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0705 hrs on 3 December 2024
PRICES ARE NOW CONFIRMED for trading interval 03-Dec-2024 06:55.
In accordance with Market Notice 121396 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412030650_confirmed] Prices for interval 03-Dec-2024 06:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0705 hrs on 3 December 2024
PRICES ARE NOW CONFIRMED for trading interval 03-Dec-2024 06:50.
In accordance with Market Notice 121395 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412030640_confirmed] Prices for interval 03-Dec-2024 06:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0705 hrs on 3 December 2024
PRICES ARE NOW CONFIRMED for trading interval 03-Dec-2024 06:40.
In accordance with Market Notice 121393 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning .
Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines
Cancellation time: 02/12/2024 22:45
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 121388
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 02/12/2024 21:54
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 121366
Auto-generated on behalf of Manager NEM Real Time Operations