Market Notices

120581SETTLEMENTS RESIDUE17/11/2024 08:35:27 PM

[EventId:202411172035_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 17 November 2024 20:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2035 hrs on 17 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 November 2024.

Refer to market notice: 120561

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2035 hrs on 17 November 2024.

This is an AEMO autogenerated Market Notice.
     
120579RESERVE NOTICE17/11/2024 07:56:58 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120575 is cancelled at 1945 hrs 17/11/2024.

Manager NEM Real Time Operations
     
120577MARKET INTERVENTION17/11/2024 07:17:16 PM

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer AEMO Electricity Participant Notice 120554

The MINTARO MINTARO GAS direction is now expected to stay in place until 2130 hrs 18/11/2024.

The direction update is issued at 1915 hrs 17/11/2024.

Manager NEM Real Time Operations
     
120575RESERVE NOTICE17/11/2024 05:53:51 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1830 hrs 18/11/2024 to 1900 hrs 18/11/2024.
The forecast capacity reserve requirement is 1061 MW.
The minimum capacity reserve available is 1045 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120572RESERVE NOTICE17/11/2024 05:05:46 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120546 is cancelled at 1700 hrs 17/11/2024.

Manager NEM Real Time Operations
     
120563PRICES SUBJECT TO REVIEW17/11/2024 04:10:15 PM

[EventId:202411171615_review] Prices for interval 17-Nov-2024 16:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1610 hrs on 17 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Nov-2024 16:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120562PRICES SUBJECT TO REVIEW17/11/2024 04:05:18 PM

[EventId:202411171610_review] Prices for interval 17-Nov-2024 16:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 17 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Nov-2024 16:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120561SETTLEMENTS RESIDUE17/11/2024 04:06:41 PM

[EventId:202411171605_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 17 November 2024 16:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 17 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1605 hrs on 17 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120560PRICES SUBJECT TO REVIEW17/11/2024 04:01:13 PM

[EventId:202411171605_review] Prices for interval 17-Nov-2024 16:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 17 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Nov-2024 16:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm