[EventId:202412081950_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 December 2024 19:50
Issued by Australian Energy Market Operator Ltd at 1950 hrs on 8 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2024.
Refer to market notice: 121639
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1950 hrs on 8 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412081830_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 December 2024 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 8 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1830 hrs on 8 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202412081835_review] Prices for interval 08-Dec-2024 18:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081830_review] Prices for interval 08-Dec-2024 18:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081825_review] Prices for interval 08-Dec-2024 18:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 08/12/2024 to 1930 hrs 08/12/2024.
The forecast capacity reserve requirement is 990 MW.
The minimum capacity reserve available is 920 MW.
Manager NEM Real Time Operations
[EventId:202412081820_review] Prices for interval 08-Dec-2024 18:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081815_review] Prices for interval 08-Dec-2024 18:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081810_review] Prices for interval 08-Dec-2024 18:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.