Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024
Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024
The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121101 is cancelled at 1645 hrs 27/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.
The Actual LOR2 condition is forecast to exist until 1700 hrs.
The capacity reserve required is 685 MW
The minimum reserve available is 412 MW
AEMO is seeking an immediate market response.
Manager NEM Real Time Operations
Declaration of electricity market resumption
Declaration of electricity market resumption
Refer initial AEMO Electricity Market Notice 118149
AEMO declares that the suspension of the spot market in New South Wales, Queensland, South Australia, Tasmania and Victoria will end at 1510 hrs on 05 September 2024.
AEMO has taken sufficient steps to exclude the original event having influence on market processes and AEMO assesses that the possibility of suspending the spot market within the next 24 hours due to the same cause is minimal. AEMO also determines that it can operate the market in accordance with the provisions of the NER.
Relevant Market Notices issued under this suspension: 118149
Manager NEM Real Time Operations
Declaration of electricity market suspension
Declaration of electricity market suspension
AEMO declares the spot market suspended in New South Wales, Queensland, South Australia, Tasmania and Victoria with Market Suspension Schedule Pricing (refer NER clause 3.14.5(b)) from Trading Interval 1355 hrs on 5 September 2024 until further notice.
Dispatch prices for the first one or two dispatch intervals of this market suspension will be reviewed manually.
Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024
Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024
The Actual LOR2 Condition in the VIC Region advised in AEMO Electricity Market Notice No.114589 is cancelled at 1614 hrs 13/02/2024.
Manager NEM Real Time Operations
Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
The Actual LOR3 Condition in the VIC region advised in AEMO Electricity Market Notice No.114604 is cancelled at 1515 hrs 13/02/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Customer load shedding of non-interruptible load is occurring in the VIC region as a result of a shortfall of available capacity reserves.
An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 1420 hrs.
The Actual LOR3 condition is not forecast in Pre Dispatch.
The maximum load to be interrupted is up to 450 MW from 1420 hrs 13/02/2024
Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the NSW region - 14/12/2023
Cancellation of Actual (LOR2) condition in the NSW region - 14/12/2023
The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112362 is cancelled at 1810 hrs 14/12/2023.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 14/12/2023
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 14/12/2023
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR2 condition is not forecast in Pre Dispatch
The capacity reserve required is 690 MW
The minimum reserve available is 678 MW
AEMO is seeking an immediate market response.
An insufficient market response may require AEMO to implement a AEMO intervention event.
Manager NEM Real Time Operations