Market Notices

120912MARKET INTERVENTION25/11/2024 01:11:39 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2330 hrs 26/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
120909NON-CONFORMANCE25/11/2024 12:30:19 PM

NON-CONFORMANCE Region NSW1 Monday, 25 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 25 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 25/11/2024 11:55 to 25/11/2024 12:30
Amount: -142 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120897RECALL GEN CAPACITY25/11/2024 08:40:06 AM

Request for Generator Recall Information for the period 27/11/2024 for Region QLD

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 120895.

Please provide Generator Recall Information for the period from 27/11/2024, by 1500 hrs on 25/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
120896RECALL GEN CAPACITY25/11/2024 08:38:28 AM

Request for Generator Recall Information for the period 27/11/2024 for Region NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 120894, and 120892.

Please provide Generator Recall Information for the period from 27/11/2024, by 1500 hrs on 25/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
120891NON-CONFORMANCE24/11/2024 07:45:13 PM

NON-CONFORMANCE Region QLD1 Sunday, 24 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 24 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 24/11/2024 19:00 to 24/11/2024 19:45
Amount: 13 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120877NON-CONFORMANCE24/11/2024 10:35:23 AM

NON-CONFORMANCE Region QLD1 Sunday, 24 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 24 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WHITSF1
Duration: 24/11/2024 09:25 to 24/11/2024 10:35
Amount: 53 MW
Constraint: NC-Q_WHITSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120786NON-CONFORMANCE22/11/2024 08:25:28 AM

NON-CONFORMANCE Region NSW1 Friday, 22 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 22 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 22/11/2024 08:05 to 22/11/2024 08:25
Amount: -73 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120747MARKET INTERVENTION21/11/2024 01:42:14 PM

Cancellation - AEMO Intervention Event - SA region 15/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 15/11/2024

Refer to Market Notice 120499

The AEMO Intervention Event and all associated directions are cancelled from 1335 hrs on 21/11/2024.


Manager NEM Real Time Operations
     
120745MARKET INTERVENTION21/11/2024 01:35:59 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 120723

Direction is cancelled from: 1330 hrs 21/11/2024

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm