121798SETTLEMENTS RESIDUE12/12/2024 04:25:21 PM

[EventId:202412121625_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 12 December 2024 16:25

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1625 hrs on 12 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1625 hrs on 12 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121797RESERVE NOTICE12/12/2024 03:59:41 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121785 is cancelled at 1500 hrs on 12/12/2024.

AEMO Operations
     
121785RESERVE NOTICE12/12/2024 02:07:57 PM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 1530 hrs to 1600 hrs 17/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 54 MW at 1530 hrs.

2. From 1630 hrs to 1730 hrs 17/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 45 MW at 1630 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121775RESERVE NOTICE12/12/2024 12:22:54 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121768 is cancelled at 1100 hrs on 12/12/2024.

AEMO Operations
     
121768RESERVE NOTICE12/12/2024 10:21:25 AM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1530 hrs to 1600 hrs 17/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 60 MW at 1530 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121766MARKET INTERVENTION12/12/2024 09:31:31 AM

Cancellation - AEMO Intervention Event - SA region 11/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 06/12/2024

Refer to Market Notice 121721

The AEMO Intervention Event and all associated directions are cancelled from 0930 hrs on 12/12/2024.


Manager NEM Real Time Operations
     
121763MARKET INTERVENTION12/12/2024 09:30:08 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 121722

Direction is cancelled from: 0930 hrs 12/12/2024

Manager NEM Real Time Operations
     
121760RESERVE NOTICE12/12/2024 09:04:31 AM

STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121734 has been updated at 0800 hrs 12/12/2024 to the following:

From 1500 hrs to 1930 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 733 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121739INTER-REGIONAL TRANSFER12/12/2024 01:37:40 AM

Inter-Regional Transfer limit variation - Basslink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Basslink

There has been an unplanned outage of the Basslink interconnector.

The following constraint set was invoked at 0130 hrs 12/12/2024

I-BL_ZERO

The constraint set contains the following interconnector on the left hand side.

T-V-MNSP1

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm