NON-CONFORMANCE Region NSW1 Sunday, 1 December 2024
NON-CONFORMANCE NSW1 Region Sunday, 1 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GOONSF1
Duration: 01/12/2024 11:50 to 01/12/2024 12:20
Amount: 54 MW
Constraint: NC-N_GOONSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Sunday, 1 December 2024
NON-CONFORMANCE NSW1 Region Sunday, 1 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GOONSF1
Duration: 01/12/2024 09:55 to 01/12/2024 11:20
Amount: 35 MW
Constraint: NC-N_GOONSF1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Update of the suspect Lack Of Reserve Level 3 (LOR3) condition in the NSW Region on 06/12/2024
The suspect LOR3 condition advised in AEMO Electricity Market Notice No. 121292 has been reviewed.
AEMO considers this forecast LOR3 condition invalid. Subsequent STPASA runs are producing valid solutions.
AEMO Operations
STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the NSW Region on 06/12/2024
AEMO considers that there is a suspect Forecast LOR3 condition for the NSW region for the following period:
From 1630 hrs 06/12/2024 to 1700 hrs 06/12/2024.
AEMO is currently investigating this LOR3 forecast condition to confirm whether they are valid.
AEMO Operations
[EventId:202411291530_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 November 2024 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 29 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 November 2024.
Refer to market notice: 121235
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1530 hrs on 29 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411291300_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 November 2024 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 29 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1300 hrs on 29 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411291230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 November 2024 12:30
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 29 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 November 2024.
Refer to market notice: 121233
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 29 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411291035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 November 2024 10:35
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 29 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 29 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411290930_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 November 2024 09:30
Issued by Australian Energy Market Operator Ltd at 0930 hrs on 29 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 November 2024.
Refer to market notice: 121223
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 0930 hrs on 29 November 2024.