STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120672 has been updated at 0450 hrs 20/11/2024 to the following:
[1.] From 1400 hrs 26/11/2024 to 1530 hrs 26/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 116 MW.
[2.] From 1930 hrs 26/11/2024 to 2030 hrs 26/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 213 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120677 has been updated at 0445 hrs 20/11/2024 to the following:
From 1530 hrs 25/11/2024 to 1930 hrs 25/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 23 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120671 has been updated at 2230 hrs on 19/11/2024 to the following:
[1.] From 1530 hrs 26/11/2024 to 1900 hrs 26/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 397 MW at 1800 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120625
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 21/11/2024.
The direction update is issued at 1700 hrs 19/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120626
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 21/11/2024.
The direction update is issued at 1700 hrs 19/11/2024.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120652 and 120638 has been updated at 1400 hrs 19/11/2024 to the following:
From 1600 hrs to 1930 hrs 25/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 236 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
1. From 1430 hrs to 1600 hrs 26/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 110 MW.
2. From 1900 hrs to 2030 hrs 26/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 77 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1600 hrs to 1900 hrs 26/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 199 MW at 1730 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
NON-CONFORMANCE Region NSW1 Tuesday, 19 November 2024
NON-CONFORMANCE NSW1 Region Tuesday, 19 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: AVLSF1
Duration: 19/11/2024 10:40 to 19/11/2024 10:50
Amount: 19 MW
Constraint: NC-N_AVLSF1
Auto-generated on behalf of Manager NEM Real Time Operations