Filter by category
Filter by Date
Cancellation of Actual (LOR1) condition in the NSW region - 26/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 26/11/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121009 is cancelled at 2015 hrs 26/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 886 MW
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120972 is cancelled at 16:50 hrs 26/11/2024.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120984 is cancelled at 1545 hrs 26/11/2024.
Manager NEM Real Time Operations
[EventId:202411261520_review] Prices for interval 26-Nov-2024 15:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 26 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Nov-2024 15:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411261515_review] Prices for interval 26-Nov-2024 15:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1510 hrs on 26 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Nov-2024 15:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411261510_review] Prices for interval 26-Nov-2024 15:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 26 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Nov-2024 15:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120978 has been updated at 1500 hrs 26/11/2024 to the following:
From 0630 hrs to 1500 hrs 29/11/2024.
The forecast capacity reserve requirement is 1421 MW.
The minimum capacity reserve available is 1200 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120969 has been updated at 1500 hrs 26/11/2024 to the following:
1. From 0830 hrs to 1000 hrs 28/11/2024.
The forecast capacity reserve requirement is 1340 MW.
The minimum capacity reserve available is 1294 MW.
2. From 1030 hrs to 2300 hrs 28/11/2024.
The forecast capacity reserve requirement is 1523 MW.
The minimum capacity reserve available is 213 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations