NON-CONFORMANCE Region NSW1 Wednesday, 4 December 2024
NON-CONFORMANCE NSW1 Region Wednesday, 4 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 04/12/2024 06:25 to 04/12/2024 06:40
Amount: -16 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 3 December 2024
NON-CONFORMANCE NSW1 Region Tuesday, 3 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 03/12/2024 11:05 to 03/12/2024 11:15
Amount: -58 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
INC0138848 - ALERT - EMMS - RESOLVED
The service interruption relating to the Electricity Market Management System service has been resolved.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
INC0138848 - ALERT - EMMS
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to the Electricity Market Management System service.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)
Refer AEMO Electricity Market Notice 121376
AEMO has been notified that the controls to vary Murraylink output are now available.
Constraint set I-CTRL_ISSUE_ML revoked at 1420 hrs.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)
Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)
AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_ML invoked from 1350 hrs.
The constraint set contains equations with the following interconnector on the LHS:
V-S-MNSP1
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Sunday, 1 December 2024
NON-CONFORMANCE NSW1 Region Sunday, 1 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GOONSF1
Duration: 01/12/2024 11:50 to 01/12/2024 12:20
Amount: 54 MW
Constraint: NC-N_GOONSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Sunday, 1 December 2024
NON-CONFORMANCE NSW1 Region Sunday, 1 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GOONSF1
Duration: 01/12/2024 09:55 to 01/12/2024 11:20
Amount: 35 MW
Constraint: NC-N_GOONSF1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Update of the suspect Lack Of Reserve Level 3 (LOR3) condition in the NSW Region on 06/12/2024
The suspect LOR3 condition advised in AEMO Electricity Market Notice No. 121292 has been reviewed.
AEMO considers this forecast LOR3 condition invalid. Subsequent STPASA runs are producing valid solutions.
AEMO Operations