Market Notices

121021RESERVE NOTICE27/11/2024 07:27:45 AM

PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 84 MW at approximately 1530 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120979NON-CONFORMANCE26/11/2024 01:50:12 PM

NON-CONFORMANCE Region NSW1 Tuesday, 26 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 26 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 26/11/2024 13:35 to 26/11/2024 13:50
Amount: 11 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120968RESERVE NOTICE26/11/2024 12:54:48 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120965 is cancelled at 1200 hrs on 26/11/2024.

No LOR3 condition is currently forecast in the STPASA period.


AEMO Operations
     
120965RESERVE NOTICE26/11/2024 11:02:40 AM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs to 1500 hrs 28/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 118 MW at 1430 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120949RESERVE NOTICE26/11/2024 03:07:47 AM

[STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120914 is cancelled at 0230 hrs on 26/11/2024.

No LOR3 condition is currently forecast in the STPASA period.

Manager NEM RTO
     
120919INTER-REGIONAL TRANSFER25/11/2024 02:03:31 PM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of Murraylink.

The following constraint set was invoked at 1405 hrs 25/11/2024

I-ML_ZERO

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
120914RESERVE NOTICE25/11/2024 03:25:34 PM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1400 hrs to 1500 hrs 28/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 205 MW at 1430 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120913RESERVE NOTICE25/11/2024 03:20:23 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120904 is cancelled at 1400 hrs on 25/11/2024.

AEMO Operations
     
120909NON-CONFORMANCE25/11/2024 12:30:19 PM

NON-CONFORMANCE Region NSW1 Monday, 25 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 25 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 25/11/2024 11:55 to 25/11/2024 12:30
Amount: -142 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     