121114SETTLEMENTS RESIDUE27/11/2024 05:45:17 PM

[EventId:202411271745_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 November 2024 17:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 27 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.

Refer to market notice: 121112

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1745 hrs on 27 November 2024.

This is an AEMO autogenerated Market Notice.
     
121113RESERVE NOTICE27/11/2024 05:42:16 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121087 is cancelled at 1740 hrs 27/11/2024.

Manager NEM Real Time Operations
     
121112SETTLEMENTS RESIDUE27/11/2024 05:30:25 PM

[EventId:202411271730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 November 2024 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 27 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 27 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121111SETTLEMENTS RESIDUE27/11/2024 05:03:44 PM

[EventId:202411271700_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 November 2024 17:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 27 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.

Refer to market notice: 121093

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1700 hrs on 27 November 2024.

This is an AEMO autogenerated Market Notice.
     
121110MARKET INTERVENTION27/11/2024 04:47:35 PM

End of RERT Dispatch - 27/11/2024 and End of intervention event

AEMO ELECTRICITY MARKET NOTICE.
End of Reliability and Emergency Reserve Trader (RERT) dispatch for - NSW1 Region - 27/11/2024 and end of AEMO Intervention Event.

Refer AEMO Electricity Market Notices 121102
Activation of reserve contract(s) has ended.
The reserve contract(s) were activated from 15:45 hrs 27/11/2024 to 16:45 hrs 27/11/2024
The AEMO Intervention Event ended from 16:45 hrs 27/11/2024


Manager NEM Real Time Operations
     
121109MARKET INTERVENTION27/11/2024 04:53:15 PM

Cancellation - AEMO Intervention Event - NSW region 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - NSW region 27/11/2024

Refer to Market Notice 121070

The AEMO Intervention Event and all associated directions are cancelled from 1645 hrs on 27/11/2024.


Manager NEM Real Time Operations
     
121108MARKET INTERVENTION27/11/2024 04:52:02 PM

Cancellation: Direction issued to: Munmorah Battery ProjectCo Pty Ltd - WARATAHBESS1

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Munmorah Battery ProjectCo Pty Ltd - WARATAHBESS1

Refer to Market Notice 121083

Direction is cancelled from: 1645 hrs 27/11/2024

Manager NEM Real Time Operations
     
121107MARKET INTERVENTION27/11/2024 04:49:20 PM

Cancellation: Direction issued to: Iberdrola Australia Wallgrove Pty Limited - WALLGROVE BESS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Iberdrola Australia Wallgrove Pty Limited - WALLGROVE BESS

Refer to Market Notice 121067

Direction is cancelled from: 1645 hrs 27/11/2024

Manager NEM Real Time Operations
     
121105RESERVE NOTICE27/11/2024 04:45:09 PM

Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024

The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121101 is cancelled at 1645 hrs 27/11/2024.