STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1430 hrs 10/12/2024 to 1500 hrs 10/12/2024.
The forecast capacity reserve requirement is 819 MW.
The minimum capacity reserve available is 802 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202412081835_review] Prices for interval 08-Dec-2024 18:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081830_review] Prices for interval 08-Dec-2024 18:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081825_review] Prices for interval 08-Dec-2024 18:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081820_review] Prices for interval 08-Dec-2024 18:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081815_review] Prices for interval 08-Dec-2024 18:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081810_review] Prices for interval 08-Dec-2024 18:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081805_review] Prices for interval 08-Dec-2024 18:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 08/12/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_5667C22F from 1600 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations