Filter by category
Filter by Date
INC0138597 - ALERT - EMMS
AEMO is experiencing a service interruption relating to the Electricity Market Management System service.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
NON-CONFORMANCE Region NSW1 Monday, 25 November 2024
NON-CONFORMANCE NSW1 Region Monday, 25 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 25/11/2024 11:55 to 25/11/2024 12:30
Amount: -142 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120902 has been updated at 1100 hrs on 25/11/2024 to the following:
From 1530 hrs to 1930 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 227 MW at 1530 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120894 has been updated at 0800 hrs on 25/11/2024 to the following:
From 1500 hrs to 2000 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 351 MW at 1530 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120879 has been updated at 0430 hrs on 25/11/2024 to the following:
[1.] From 1130 hrs 27/11/2024 to 1930 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 1731 MW at 1430 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 24 November 2024
NON-CONFORMANCE QLD1 Region Sunday, 24 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 24/11/2024 19:00 to 24/11/2024 19:45
Amount: 13 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120876 has been updated at 1445 hrs on 24/11/2024 to the following:
[1.] From 1200 hrs 27/11/2024 to 1900 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 1052 MW at 1430 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 24 November 2024
NON-CONFORMANCE QLD1 Region Sunday, 24 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WHITSF1
Duration: 24/11/2024 09:25 to 24/11/2024 10:35
Amount: 53 MW
Constraint: NC-Q_WHITSF1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120864 has been updated at 0930 hrs on 24/11/2024 to the following:
1.] From 1330 hrs 27/11/2024 to 1830 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 523 MW at 1430 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations