121038MARKET INTERVENTION27/11/2024 09:58:34 AM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - NSW1 Region- 27/11/2024

Refer to AEMO Electricity Market Notice no. 121022.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
14:30 to 20:30 hrs 27/11/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations
     
121032MARKET INTERVENTION27/11/2024 09:48:46 AM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 121004

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1730 hrs 27/11/2024.

The direction update is issued at 0945 hrs 27/11/2024.

Manager NEM Real Time Operations
     
121031MARKET INTERVENTION27/11/2024 09:47:43 AM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 121003

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 27/11/2024.

The direction update is issued at 0945 hrs 27/11/2024.

Manager NEM Real Time Operations
     
121024RESERVE NOTICE27/11/2024 09:51:07 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121015 has been updated at 0900 hrs 27/11/2024 to the following:

From 1530 hrs to 1830 hrs 29/11/2024.
The forecast capacity reserve requirement is 1357 MW.
The minimum capacity reserve available is 965 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
121023RESERVE NOTICE27/11/2024 09:49:56 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121014 has been updated at 0900 hrs 27/11/2024 to the following:

From 1730 hrs to 1800 hrs 28/11/2024.
The forecast capacity reserve requirement is 1154 MW.
The minimum capacity reserve available is 1014 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121022RESERVE NOTICE27/11/2024 07:35:08 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120974 has been updated at 0730 hrs to the following:

[1.] From 1400 hrs 27/11/2024 to 1530 hrs 27/11/2024.
The forecast capacity reserve requirement is 820 MW.
The minimum capacity reserve available is 82 MW.

[2.] From 1700 hrs 27/11/2024 to 1900 hrs 27/11/2024.
The forecast capacity reserve requirement is 800 MW.
The minimum capacity reserve available is 50 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121021RESERVE NOTICE27/11/2024 07:27:45 AM

PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 84 MW at approximately 1530 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121015RESERVE NOTICE27/11/2024 01:23:39 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120989 has been updated at 0100 hrs 27/11/2024 to the following:

[2.] From 0830 hrs 29/11/2024 to 1130 hrs 29/11/2024.
The forecast capacity reserve requirement is 1650 MW.
The minimum capacity reserve available is 1467 MW.

[3.] From 1330 hrs 29/11/2024 to 1900 hrs 29/11/2024.
The forecast capacity reserve requirement is 1487 MW.
The minimum capacity reserve available is 700 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121014RESERVE NOTICE27/11/2024 01:22:24 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120988 has been updated at 0100 hrs 27/11/2024 to the following:

[1.] From 1200 hrs 28/11/2024 to 2130 hrs 28/11/2024.
The forecast capacity reserve requirement is 1367 MW.
The minimum capacity reserve available is 489 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     