Cancellation of Actual (LOR1) condition in the NSW region - 12/12/2024
Cancellation of Actual (LOR1) condition in the NSW region - 12/12/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121803 is cancelled at 1945 hrs 12/12/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 12/12/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1338 MW.
Manager NEM Real Time Operations
[EventId:202412120145_confirmed] Prices for interval 12-Dec-2024 01:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 01:45.
In accordance with Market Notice 121741 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412120205_confirmed] Prices for interval 12-Dec-2024 02:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 02:05.
In accordance with Market Notice 121745 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412120200_confirmed] Prices for interval 12-Dec-2024 02:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 02:00.
In accordance with Market Notice 121744 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412120155_confirmed] Prices for interval 12-Dec-2024 01:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 01:55.
In accordance with Market Notice 121743 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412120150_confirmed] Prices for interval 12-Dec-2024 01:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 01:50.
In accordance with Market Notice 121742 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412120140_confirmed] Prices for interval 12-Dec-2024 01:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 01:40.
In accordance with Market Notice 121740 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Inter-Regional Transfer limit variation - Basslink
Inter-Regional Transfer limit variation - Basslink
There has been an unplanned outage of the Basslink interconnector.
The following constraint set was invoked at 0130 hrs 12/12/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations