Market Notices

121508MINIMUM SYSTEM LOAD06/12/2024 02:43:31 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 08/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 08/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1590 MW
o MSL2 - 1090 MW
o MSL3 - 590 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

1. From 1200 hrs 08/12/2024 to 1330 hrs 08/12/2024. Minimum regional demand is forecast to be 1496 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
121169PRICE ADJUSTMENT28/11/2024 02:18:30 PM

[EventId:202411271510_confirmed] Prices for interval 27-Nov-2024 15:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1418 hrs on 28 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 15:10.

In accordance with Market Notice 121092 AEMO has reviewed this trading interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
VIC1 -$30.00 -$29.50
RAISE60SEC
NSW1 $0.10 $0.05
QLD1 $0.10 $0.05
SA1 $0.10 $0.05
VIC1 $0.10 $0.05


This is an AEMO autogenerated Market Notice.
     
121105RESERVE NOTICE27/11/2024 04:45:09 PM

Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024

The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121101 is cancelled at 1645 hrs 27/11/2024.

Manager NEM Real Time Operations
     
121101RESERVE NOTICE27/11/2024 03:48:50 PM

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.

The Actual LOR2 condition is forecast to exist until 1700 hrs.
The capacity reserve required is 685 MW
The minimum reserve available is 412 MW

AEMO is seeking an immediate market response.

Manager NEM Real Time Operations
     
121008POWER SYSTEM EVENTS26/11/2024 04:55:00 PM

Non-credible contingency event - NSW region - 26/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 26/11/2024

At 1637 hrs Uranquinty Unit 12 tripped and at 1639 hrs Uranquinty Units 11 and 13 tripped.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
120800PRICE ADJUSTMENT22/11/2024 11:27:26 AM

[EventId:202411221115_confirmed] Prices for interval 22-Nov-2024 11:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1126 hrs on 22 November 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:15.

In accordance with Market Notice 120795 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs applied. Prices have been carried forward from the previous dispatch interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 $64.00 $25.81
QLD1 $62.79 $26.90
SA1 $8.61 $11.91
VIC1 $8.95 $12.00
LOWER1SEC
NSW1 $0.94 $0.10
QLD1 $0.94 $0.10
SA1 $0.94 $0.10
VIC1 $0.94 $0.10
LOWER60SEC
NSW1 $4.64 $1.82
QLD1 $4.64 $1.82
SA1 $4.64 $1.82
VIC1 $4.64 $1.82
LOWER6SEC
NSW1 $9.69 $4.89
QLD1 $9.69 $4.89
SA1 $9.69 $4.89
VIC1 $9.69 $4.89
LOWERREG
NSW1 $9.99 $19.85
QLD1 $9.99 $19.85
SA1 $9.99 $19.85
VIC1 $9.99 $19.85
RAISE1SEC
NSW1 $0.84 $0.05
QLD1 $0.84 $0.05
SA1 $0.84 $0.05
TAS1 $0.84 $0.05
VIC1 $0.84 $0.05
RAISE5MIN
NSW1 $0.05 $0.10
QLD1 $0.05 $0.10
SA1 $0.05 $0.10
VIC1 $0.05 $0.10
RAISE60SEC
NSW1 $0.00 $0.01
QLD1 $0.00 $0.01
SA1 $0.00 $0.01
VIC1 $0.00 $0.01
RAISE6SEC
NSW1 $0.01 $0.00
QLD1 $0.01 $0.00
SA1 $0.01 $0.00
VIC1 $0.01 $0.00
RAISEREG
NSW1 $7.99 $1.00
QLD1 $7.99 $1.00
SA1 $7.99 $1.00
VIC1 $7.99 $1.00


This is an AEMO autogenerated Market Notice.
     
120797PRICE ADJUSTMENT22/11/2024 11:17:32 AM

[EventId:202411221110_confirmed] Prices for interval 22-Nov-2024 11:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1117 hrs on 22 November 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:10.

In accordance with Market Notice 120794 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs applied. Prices have been carried forward from the previous dispatch interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 $150.01 $25.81
QLD1 $143.43 $26.90
SA1 $53.81 $11.91
VIC1 $55.02 $12.00
LOWER5MIN
NSW1 $1.57 $0.39
QLD1 $1.57 $0.39
SA1 $1.57 $0.39
VIC1 $1.57 $0.39
LOWER60SEC
NSW1 $4.64 $1.82
QLD1 $4.64 $1.82
SA1 $4.64 $1.82
VIC1 $4.64 $1.82
LOWER6SEC
NSW1 $9.69 $4.89
QLD1 $9.69 $4.89
SA1 $9.69 $4.89
VIC1 $9.69 $4.89
LOWERREG
NSW1 $20.90 $19.85
QLD1 $20.90 $19.85
SA1 $20.90 $19.85
VIC1 $20.90 $19.85
RAISE1SEC
NSW1 $0.10 $0.05
QLD1 $0.10 $0.05
SA1 $0.10 $0.05
TAS1 $0.10 $0.05
VIC1 $0.10 $0.05
RAISE5MIN
NSW1 $0.05 $0.10
QLD1 $0.05 $0.10
SA1 $0.05 $0.10
VIC1 $0.05 $0.10
RAISE60SEC
NSW1 $0.05 $0.01
QLD1 $0.05 $0.01
SA1 $0.05 $0.01
VIC1 $0.05 $0.01
RAISE6SEC
NSW1 $0.10 $0.00
QLD1 $0.10 $0.00
SA1 $0.10 $0.00
VIC1 $0.10 $0.00
RAISEREG
NSW1 $5.00 $1.00
QLD1 $5.00 $1.00
SA1 $5.00 $1.00
VIC1 $5.00 $1.00


This is an AEMO autogenerated Market Notice.
     
120306POWER SYSTEM EVENTS12/11/2024 11:43:52 AM

Update - Non-credible contingency event - VIC region - 12/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 12/11/2024

Refer AEMO Electricity Market Notice 120305

At 1135 hrs the Yallourn No 1 220 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
120305POWER SYSTEM EVENTS12/11/2024 10:55:18 AM

Non-credible contingency event - VIC region - 12/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 12/11/2024

At 1041 hrs the Yallourn No 1 220 kV bus and Yallourn Unit 4 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.


The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     