Filter by category
Filter by Date
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121558 has been updated at 0645 hrs to the following:
[1.] From 1730 hrs 07/12/2024 to 1830 hrs 07/12/2024.
The forecast capacity reserve requirement is 1786 MW.
The minimum capacity reserve available is 1760 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121550 has been updated at 0400 hrs to the following:
[1.] From 1630 hrs 07/12/2024 to 1900 hrs 07/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1284 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1600 hrs 07/12/2024 to 1700 hrs 07/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1126 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 06/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121529 is cancelled at 1645 hrs 06/12/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121527 has been updated at 1620 hrs to the following:
[1.] From 1730 hrs 06/12/2024 to 1800 hrs 06/12/2024.
The forecast capacity reserve requirement is 1643 MW.
The minimum capacity reserve available is 1610 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1630 hrs 06/12/2024 to 1830 hrs 06/12/2024.
The forecast capacity reserve requirement is 1626 MW.
The minimum capacity reserve available is 1296 MW.
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 08/12/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 08/12/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1590 MW
o MSL2 - 1090 MW
o MSL3 - 590 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 1200 hrs 08/12/2024 to 1330 hrs 08/12/2024. Minimum regional demand is forecast to be 1496 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 06/12/2024 to 1830 hrs 06/12/2024.
The forecast capacity reserve requirement is 1724 MW.
The minimum capacity reserve available is 1675 MW.
Manager NEM Real Time Operations
CHG0100220 | Pre-Production | Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages
Change Start Date & Time: 09/12/2024 08:00:00 AEST
Change End Date & Time: 10/12/2024 23:00:00 AEST
Outage Start Date & Time: 09/12/2024 08:00:00 AEST
Outage End Date & Time: 10/12/2024 23:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: This Maintenance activity may cause intermittent outages to below applications during the outage period .
Impacted Systems:
1.EMMS systems (Dispatch/ PASA/ Forecasting/ Settlements)
2.Identity Service will be running only for authentication purposes.
3.Web Portal including menu items (Markets, Internal & Public portal)
4.GSH
5.GBB
6.Any GAS systems that have a NEMA / WARA database connection.
7.MSATS
8.CDR
9.DERR
If any ongoing issues are identified, please contact the AEMO Support Hub 1300 236 600.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any