Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/12/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/12/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1430 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.
The forecast capacity reserve requirement is 1350 MW.
The minimum capacity reserve available is 1248 MW.
Manager NEM Real Time Operations
[EventId:202412061430_confirmed] Prices for interval 06-Dec-2024 14:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 6 December 2024
PRICES ARE NOW CONFIRMED for trading interval 06-Dec-2024 14:30.
In accordance with Market Notice 121506 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412061450_confirmed] Prices for interval 06-Dec-2024 14:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 6 December 2024
PRICES ARE NOW CONFIRMED for trading interval 06-Dec-2024 14:50.
In accordance with Market Notice 121513 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412061445_confirmed] Prices for interval 06-Dec-2024 14:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 6 December 2024
PRICES ARE NOW CONFIRMED for trading interval 06-Dec-2024 14:45.
In accordance with Market Notice 121512 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412061440_confirmed] Prices for interval 06-Dec-2024 14:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 6 December 2024
PRICES ARE NOW CONFIRMED for trading interval 06-Dec-2024 14:40.
In accordance with Market Notice 121509 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412061435_confirmed] Prices for interval 06-Dec-2024 14:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 6 December 2024
PRICES ARE NOW CONFIRMED for trading interval 06-Dec-2024 14:35.
In accordance with Market Notice 121507 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412061425_confirmed] Prices for interval 06-Dec-2024 14:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 6 December 2024
PRICES ARE NOW CONFIRMED for trading interval 06-Dec-2024 14:25.
In accordance with Market Notice 121505 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Forecast Minimum System Load (MSL1) condition in the VIC region on 08/12/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 08/12/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1590 MW
o MSL2 - 1090 MW
o MSL3 - 590 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 1200 hrs 08/12/2024 to 1330 hrs 08/12/2024. Minimum regional demand is forecast to be 1496 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
NON-CONFORMANCE Region NSW1 Friday, 6 December 2024
NON-CONFORMANCE NSW1 Region Friday, 6 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 06/12/2024 09:10 to 06/12/2024 09:35
Amount: -45 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations