Filter by category
Filter by Date
NON-CONFORMANCE Region NSW1 Saturday, 16 November 2024
NON-CONFORMANCE NSW1 Region Saturday, 16 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 16/11/2024 07:10 to 16/11/2024 07:35
Amount: -7 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs to 1700 hrs 17/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1270 MW.
AEMO Operations
NON-CONFORMANCE Region QLD1 Friday, 15 November 2024
NON-CONFORMANCE QLD1 Region Friday, 15 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 15/11/2024 14:20 to 15/11/2024 14:40
Amount: -14 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 15 November 2024
NON-CONFORMANCE NSW1 Region Friday, 15 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 15/11/2024 11:00 to 15/11/2024 11:15
Amount: -7 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 15 November 2024
NON-CONFORMANCE QLD1 Region Friday, 15 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 15/11/2024 00:30 to 15/11/2024 00:55
Amount: -38 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 14 November 2024
NON-CONFORMANCE QLD1 Region Thursday, 14 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 14/11/2024 17:50 to 14/11/2024 18:15
Amount: 23 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 14 November 2024
NON-CONFORMANCE QLD1 Region Thursday, 14 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 14/11/2024 16:25 to 14/11/2024 17:05
Amount: 10 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 14 November 2024
NON-CONFORMANCE QLD1 Region Thursday, 14 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 14/11/2024 16:30 to 14/11/2024 17:05
Amount: -23 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 14 November 2024
NON-CONFORMANCE QLD1 Region Thursday, 14 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 14/11/2024 12:35 to 14/11/2024 13:15
Amount: -32 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations