121050RECLASSIFY CONTINGENCY27/11/2024 10:19:16 AM

Cancellation of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Cancellation time: 27/11/2024 10:19

Constraint set(s) revoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 121030

Auto-generated on behalf of Manager NEM Real Time Operations
     
121049RESERVE NOTICE27/11/2024 10:24:23 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121022 has been updated at 1000 hrs to the following:

[1.] From 1430 hrs 27/11/2024 to 1530 hrs 27/11/2024.
The forecast capacity reserve requirement is 687 MW.
The minimum capacity reserve available is 80 MW.

[2.] From 1700 hrs 27/11/2024 to 1900 hrs 27/11/2024.
The forecast capacity reserve requirement is 776 MW.
The minimum capacity reserve available is 7 MW.

AEMO is seeking a market response.

AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1330 hrs on 27/11/2024.

Manager NEM Real Time Operations
     
121040RESERVE NOTICE27/11/2024 10:19:18 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121021 has been updated at 1000 hrs to the following:

[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 1530 hrs.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1330 hrs.

Manager NEM Real Time Operations
     
121036RESERVE NOTICE27/11/2024 09:59:59 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 121013 is cancelled at 0900 hrs 27/11/2024.

No LOR2 condition is currently forecast in the STPASA period in the QLD region.

AEMO Operations
     
121030RECLASSIFY CONTINGENCY27/11/2024 09:15:10 AM

Reclassification of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Duration: 27/11/2024 09:15 until further notice

Constraint set(s) invoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
121027RECLASSIFY CONTINGENCY27/11/2024 08:30:38 AM

Reclassification of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV

Duration: 27/11/2024 08:30 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
121024RESERVE NOTICE27/11/2024 09:51:07 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121015 has been updated at 0900 hrs 27/11/2024 to the following:

From 1530 hrs to 1830 hrs 29/11/2024.
The forecast capacity reserve requirement is 1357 MW.
The minimum capacity reserve available is 965 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
121023RESERVE NOTICE27/11/2024 09:49:56 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121014 has been updated at 0900 hrs 27/11/2024 to the following:

From 1730 hrs to 1800 hrs 28/11/2024.
The forecast capacity reserve requirement is 1154 MW.
The minimum capacity reserve available is 1014 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121022RESERVE NOTICE27/11/2024 07:35:08 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120974 has been updated at 0730 hrs to the following:

[1.] From 1400 hrs 27/11/2024 to 1530 hrs 27/11/2024.
The forecast capacity reserve requirement is 820 MW.
The minimum capacity reserve available is 82 MW.

[2.] From 1700 hrs 27/11/2024 to 1900 hrs 27/11/2024.
The forecast capacity reserve requirement is 800 MW.
The minimum capacity reserve available is 50 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     