Market Notices

120919INTER-REGIONAL TRANSFER25/11/2024 02:03:31 PM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of Murraylink.

The following constraint set was invoked at 1405 hrs 25/11/2024

I-ML_ZERO

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
120836INTER-REGIONAL TRANSFER22/11/2024 07:32:00 PM

Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024

At 1911 hrs 22/11/2024 there was an unplanned outage of the No.2 leg of Directlink.

The following constraint set(s) invoked at 1920 hrs 22/11/2024
N-X_MBTE_2

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
120831INTER-REGIONAL TRANSFER22/11/2024 05:29:01 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 2 Leg of Directlink .

The following constraint set was invoked at 1720 hrs 22/11/2024

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
120803PRICES SUBJECT TO REVIEW22/11/2024 11:40:15 AM

[EventId:202411221145_review] Prices for interval 22-Nov-2024 11:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1140 hrs on 22 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 22-Nov-2024 11:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120802PRICES SUBJECT TO REVIEW22/11/2024 11:35:11 AM

[EventId:202411221140_review] Prices for interval 22-Nov-2024 11:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 22 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 22-Nov-2024 11:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120801PRICES SUBJECT TO REVIEW22/11/2024 11:30:17 AM

[EventId:202411221135_review] Prices for interval 22-Nov-2024 11:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1130 hrs on 22 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 22-Nov-2024 11:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120799PRICES SUBJECT TO REVIEW22/11/2024 11:25:27 AM

[EventId:202411221130_review] Prices for interval 22-Nov-2024 11:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1125 hrs on 22 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 22-Nov-2024 11:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120798PRICES SUBJECT TO REVIEW22/11/2024 11:21:31 AM

[EventId:202411221125_review] Prices for interval 22-Nov-2024 11:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1120 hrs on 22 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 22-Nov-2024 11:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120796PRICES SUBJECT TO REVIEW22/11/2024 11:15:27 AM

[EventId:202411221120_review] Prices for interval 22-Nov-2024 11:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1115 hrs on 22 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 22-Nov-2024 11:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     