120837SETTLEMENTS RESIDUE22/11/2024 07:40:15 PM

[EventId:202411221940_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 November 2024 19:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1940 hrs on 22 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 November 2024.

Refer to market notice: 120834

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1940 hrs on 22 November 2024.

This is an AEMO autogenerated Market Notice.
     
120834SETTLEMENTS RESIDUE22/11/2024 06:20:27 PM

[EventId:202411221820_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 November 2024 18:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1820 hrs on 22 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1820 hrs on 22 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120830RESERVE NOTICE22/11/2024 05:08:24 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120827 has been updated at 1600 hrs 22/11/2024 to the following:

From 1700 hrs 27/11/2024 to 1900 hrs 27/11/2024.
The forecast capacity reserve requirement is 525 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120829RESERVE NOTICE22/11/2024 05:07:30 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120826 has been updated at 1600 hrs 22/11/2024 to the following:

[1.] From 1230 hrs 27/11/2024 to 1800 hrs 27/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 31 MW.

[2.] From 1830 hrs 27/11/2024 to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 99 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120827RESERVE NOTICE22/11/2024 04:04:11 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120819 has been updated at 1500 hrs 22/11/2024 to the following:

From 1700 hrs to 1900 hrs 27/11/2024.
The forecast capacity reserve requirement is 525 MW.
The minimum capacity reserve available is 110 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
120826RESERVE NOTICE22/11/2024 04:03:16 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120818 has been updated at 1500 hrs 22/11/2024 to the following:

From 1330 hrs to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 64 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120825RESERVE NOTICE22/11/2024 03:58:10 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120756 has been updated at 1400 hrs 22/11/2024 to the following:

1. From 1700 hrs to 1800 hrs 27/11/2024.
The forecast capacity reserve requirement is 1005 MW.
The minimum capacity reserve available is 613 MW.

2. From 1830 hrs to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 1005 MW.
The minimum capacity reserve available is 525 MW.


AEMO Operations
     
120824RESERVE NOTICE22/11/2024 03:40:14 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120755 is cancelled at 1400 hrs 22/11/2024.

AEMO Operations
     
120823RESERVE NOTICE22/11/2024 03:41:30 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120757 is cancelled at 1400 hrs 22/11/2024.

AEMO Operations
     