121078PRICES UNCHANGED27/11/2024 01:19:10 PM

[EventId:202411271310_confirmed] Prices for interval 27-Nov-2024 13:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 27 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 13:10.

In accordance with Market Notice 121071 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121077PRICES UNCHANGED27/11/2024 01:16:22 PM

[EventId:202411271305_confirmed] Prices for interval 27-Nov-2024 13:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 27 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 13:05.

In accordance with Market Notice 121068 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121076PRICES UNCHANGED27/11/2024 01:15:15 PM

[EventId:202411271300_confirmed] Prices for interval 27-Nov-2024 13:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 27 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 13:00.

In accordance with Market Notice 121065 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121075PRICES UNCHANGED27/11/2024 01:17:26 PM

[EventId:202411271250_confirmed] Prices for interval 27-Nov-2024 12:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 27 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 12:50.

In accordance with Market Notice 121061 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121073RECLASSIFY CONTINGENCY27/11/2024 01:13:31 PM

Reclassification of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Duration: 27/11/2024 13:13 until further notice

Constraint set(s) invoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
121069RESERVE NOTICE27/11/2024 01:06:04 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1430 hrs 28/11/2024 to 1500 hrs 28/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1226 MW.

[2.] From 1600 hrs 28/11/2024 to 1700 hrs 28/11/2024.
The forecast capacity reserve requirement is 1576 MW.
The minimum capacity reserve available is 1147 MW.

[3.] From 1900 hrs 28/11/2024 to 1930 hrs 28/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1154 MW.

Manager NEM Real Time Operations
     
121064RESERVE NOTICE27/11/2024 01:07:51 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1700 hrs 28/11/2024 to 1730 hrs 28/11/2024.
The forecast capacity reserve requirement is 1248 MW.
The minimum capacity reserve available is 801 MW.

[2.] From 1830 hrs 28/11/2024 to 1930 hrs 28/11/2024.
The forecast capacity reserve requirement is 1264 MW.
The minimum capacity reserve available is 887 MW.

Manager NEM Real Time Operations
     
121058RECLASSIFY CONTINGENCY27/11/2024 11:34:15 AM

Cancellation of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV

Cancellation time: 27/11/2024 11:34

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 121027

Auto-generated on behalf of Manager NEM Real Time Operations
     
121055RESERVE NOTICE27/11/2024 11:26:41 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121053 is cancelled at 1100 hrs 27/11/2024.