Cancellation of Actual (LOR1) condition in the NSW region - 22/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 22/11/2024
The Actual LOR1 Condition in the NSW region advised in AEMO Electricity Market Notice No.120833 is cancelled at 1838 hrs 22/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 22/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 22/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.
The forecast capacity reserve requirement is 1396 MW.
The minimum capacity reserve available is 1348 MW.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 15/11/2024
Cancellation - AEMO Intervention Event - SA region 15/11/2024
Refer to Market Notice 120499
The AEMO Intervention Event and all associated directions are cancelled from 1335 hrs on 21/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 120723
Direction is cancelled from: 1330 hrs 21/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 120722
Direction is cancelled from: 1330 hrs 21/11/2024
Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 21/11/2024
Network Augmentation Commissioned - QLD Region - 21/11/2024
Commissioned:
Belmont No.2 275 kV 150 MVar reactor
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120680
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 21/11/2024.
The direction update is issued at 1630 hrs 20/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120679
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1330 hrs 21/11/2024.
The direction update is issued at 1630 hrs 20/11/2024.
Manager NEM Real Time Operations
Project Energy Connect (PEC-1) testing 21st November 2024 0600-0900 for flows in both directions
Refer to market notice 120307
There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 21st November from 06:00hrs to 09:00hrs
This test includes includes a fast runback of Murraylink.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake