121804RESERVE NOTICE12/12/2024 07:52:07 PM

Cancellation of Actual (LOR1) condition in the NSW region - 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 12/12/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121803 is cancelled at 1945 hrs 12/12/2024.

Manager NEM Real Time Operations
     
121803RESERVE NOTICE12/12/2024 07:17:45 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 12/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1830 hrs.

The Actual LOR1 condition is forecast to exist until 1930 hrs.

The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1338 MW.


Manager NEM Real Time Operations
     
121798SETTLEMENTS RESIDUE12/12/2024 04:25:21 PM

[EventId:202412121625_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 12 December 2024 16:25

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1625 hrs on 12 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1625 hrs on 12 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121755NON-CONFORMANCE12/12/2024 05:40:16 AM

NON-CONFORMANCE Region NSW1 Thursday, 12 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 12 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW02
Duration: 12/12/2024 05:35 to 12/12/2024 05:40
Amount: -31 MW
Constraint: NC-N_BW02

Auto-generated on behalf of Manager NEM Real Time Operations
     
121745PRICES SUBJECT TO REVIEW12/12/2024 02:00:17 AM

[EventId:202412120205_review] Prices for interval 12-Dec-2024 02:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0200 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 02:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121744PRICES SUBJECT TO REVIEW12/12/2024 01:55:24 AM

[EventId:202412120200_review] Prices for interval 12-Dec-2024 02:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0155 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 02:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121743PRICES SUBJECT TO REVIEW12/12/2024 01:50:16 AM

[EventId:202412120155_review] Prices for interval 12-Dec-2024 01:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0150 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121742PRICES SUBJECT TO REVIEW12/12/2024 01:45:20 AM

[EventId:202412120150_review] Prices for interval 12-Dec-2024 01:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0145 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121741PRICES SUBJECT TO REVIEW12/12/2024 01:40:21 AM

[EventId:202412120145_review] Prices for interval 12-Dec-2024 01:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0140 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     