INTENTION TO IMPLEMENT an AEMO INTERVENTION EVENT WITH RERT
AEMO Intervention Event, Reliability and Emergency Reserve Trader (RERT) - NSW1 Region - 27/11/2024
Refer to AEMO Electricity Market Notice no. 121038.
AEMO has entered into a reserve contract and may implement a AEMO Intervention Event by dispatching that reserve contract to maintain the power system in a Reliable operating state during the following period of time;
14:30 to 20:30 hrs 27/11/2024
If reserve is required, the period of activation or dispatch will be within this period, but may not be for all the entire period.
AEMO will issue a further advice if the reserve contract is dispatched/activated.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 27 November 2024
NON-CONFORMANCE QLD1 Region Wednesday, 27 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 27/11/2024 09:45 to 27/11/2024 10:25
Amount: 36 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 27 November 2024
NON-CONFORMANCE QLD1 Region Wednesday, 27 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 27/11/2024 09:55 to 27/11/2024 10:25
Amount: -17 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 121032
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1830 hrs 27/11/2024.
The direction update is issued at 1035 hrs 27/11/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121021 has been updated at 1000 hrs to the following:
[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 1530 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1330 hrs.
Manager NEM Real Time Operations
INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - NSW1 Region- 27/11/2024
Refer to AEMO Electricity Market Notice no. 121022.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
14:30 to 20:30 hrs 27/11/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 121004
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1730 hrs 27/11/2024.
The direction update is issued at 0945 hrs 27/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 121003
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 27/11/2024.
The direction update is issued at 0945 hrs 27/11/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 84 MW at approximately 1530 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations