118067NON-CONFORMANCE02/09/2024 02:40:19 PM

NON-CONFORMANCE Region SA1 Monday, 2 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 2 September 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 02/09/2024 11:40 to 02/09/2024 14:40
Amount: 18 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118029NON-CONFORMANCE01/09/2024 11:05:25 AM

NON-CONFORMANCE Region VIC1 Sunday, 1 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Sunday, 1 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MERCER01
Duration: 01/09/2024 11:00 to 01/09/2024 11:05
Amount: 122 MW
Constraint: NC-V_MERCER01

Auto-generated on behalf of Manager NEM Real Time Operations
     
118015NON-CONFORMANCE31/08/2024 03:25:22 PM

NON-CONFORMANCE Region SA1 Saturday, 31 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Saturday, 31 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STARHLWF
Duration: 31/08/2024 14:50 to 31/08/2024 15:25
Amount: 26 MW
Constraint: NC-S_STARHLWF

Auto-generated on behalf of Manager NEM Real Time Operations
     
118014NON-CONFORMANCE31/08/2024 03:20:26 PM

NON-CONFORMANCE Region NSW1 Saturday, 31 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 31 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: HILLSTN1
Duration: 31/08/2024 15:05 to 31/08/2024 15:20
Amount: 85 MW
Constraint: NC-N_HILLSTN1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118011NON-CONFORMANCE31/08/2024 01:55:23 PM

NON-CONFORMANCE Region SA1 Saturday, 31 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Saturday, 31 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MANNSF2
Duration: 31/08/2024 11:45 to 31/08/2024 13:55
Amount: 7 MW
Constraint: NC-S_MANNSF2

Auto-generated on behalf of Manager NEM Real Time Operations
     
117945NON-CONFORMANCE29/08/2024 03:40:16 PM

NON-CONFORMANCE Region QLD1 Thursday, 29 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 29 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GSTONE2
Duration: 29/08/2024 15:35 to 29/08/2024 15:40
Amount: 28 MW
Constraint: NC-Q_GSTONE2

Auto-generated on behalf of Manager NEM Real Time Operations
     
117909POWER SYSTEM EVENTS28/08/2024 02:17:12 AM

Update - Non-credible contingency event - VIC region - 28/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 28/08/2024

Refer AEMO Electricity Market Notice 117908

At 0134 hrs the APD No 2 Potline was returned to service.

At 0200 hrs the APD No 1 Potline was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
117908POWER SYSTEM EVENTS28/08/2024 01:02:22 AM

Non-credible contingency event - VIC region - 28/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 28/08/2024

At 0001 hrs the APD No1 Potline and the APD No 2 Potline tripped.

AEMO did not instruct load shedding.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
117783POWER SYSTEM EVENTS25/08/2024 10:33:54 AM

Update - Non-credible contingency event - TAS region - 25/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 25/08/2024

Refer AEMO Electricity Market Notice 117782

At 1023 hrs the New Norfolk A 110kV Bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm