118616PRICES SUBJECT TO REVIEW05/10/2024 04:20:13 PM

[EventId:202410051625_review] Prices for interval 05-Oct-2024 16:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1620 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118615PRICES SUBJECT TO REVIEW05/10/2024 04:15:18 PM

[EventId:202410051620_review] Prices for interval 05-Oct-2024 16:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118614PRICES SUBJECT TO REVIEW05/10/2024 04:10:24 PM

[EventId:202410051615_review] Prices for interval 05-Oct-2024 16:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1610 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118613PRICES SUBJECT TO REVIEW05/10/2024 04:05:23 PM

[EventId:202410051610_review] Prices for interval 05-Oct-2024 16:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118612PRICES SUBJECT TO REVIEW05/10/2024 04:00:25 PM

[EventId:202410051605_review] Prices for interval 05-Oct-2024 16:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118608NON-CONFORMANCE05/10/2024 11:05:23 AM

NON-CONFORMANCE Region NSW1 Saturday, 5 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 5 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WYASF1
Duration: 05/10/2024 10:30 to 05/10/2024 11:05
Amount: 31 MW
Constraint: NC-N_WYASF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118598MARKET SYSTEMS04/10/2024 04:07:21 PM

CHG0098496 | Production | QLD Marketnet Router Replacement

Change Number: CHG0098496
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: Market Network

Change Title: QLD Marketnet Router Replacement
Change Start Date & Time: 19/10/2024 14:00:53 AEST
Change End Date & Time: 19/10/2024 19:00:53 AEST

Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage on the 19th October 2024:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from QLD to NSW Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as SSL VPN's are hosted on a different device.

GASHUB: No impact is expected as GASHUB will be failed over to the NSW Datacenter.

Other Impacts will have been communicated in advance.

** FAILURE TO ENSURE VPN FAILOVER WILL RESULT IN LOSS OF MARKETNET CONNECTIVITY **
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .


     
118593NON-CONFORMANCE03/10/2024 09:10:27 PM

NON-CONFORMANCE Region QLD1 Thursday, 3 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 3 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 03/10/2024 21:00 to 03/10/2024 21:10
Amount: 26 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118586NON-CONFORMANCE03/10/2024 12:05:22 PM

NON-CONFORMANCE Region QLD1 Thursday, 3 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 3 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 03/10/2024 08:35 to 03/10/2024 12:05
Amount: -53 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     