Market Notices

118077RECLASSIFY CONTINGENCY02/09/2024 04:49:05 PM

Cancellation of a Non-Credible Contingency Event: Lindisfarne - Mornington No.1 TEE line and Lindisfarne - Mornington No.2 TEE line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Lindisfarne - Mornington No.1 TEE and Lindisfarne - Mornington No.2 TEE

Cancellation time: 02/09/2024 16:49

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 118071

Auto-generated on behalf of Manager NEM Real Time Operations
     
118076RECLASSIFY CONTINGENCY02/09/2024 04:20:12 PM

Reclassification of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV

Duration: 02/09/2024 16:20 until further notice

Constraint set(s) invoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
118072MARKET INTERVENTION02/09/2024 03:59:49 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 118060

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2300 hrs 02/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 02/09/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
118071RECLASSIFY CONTINGENCY02/09/2024 03:44:45 PM

Reclassification of a Non-Credible Contingency Event: Lindisfarne - Mornington No.1 TEE line and Lindisfarne - Mornington No.2 TEE line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Lindisfarne - Mornington No.1 TEE and Lindisfarne - Mornington No.2 TEE

Duration: 02/09/2024 15:44 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
118069RECLASSIFY CONTINGENCY02/09/2024 03:10:25 PM

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Duration: 02/09/2024 15:10 until further notice

Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Auto-generated on behalf of Manager NEM Real Time Operations
     
118068RECLASSIFY CONTINGENCY02/09/2024 03:09:01 PM

Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Duration: 02/09/2024 15:08 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
118067NON-CONFORMANCE02/09/2024 02:40:19 PM

NON-CONFORMANCE Region SA1 Monday, 2 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 2 September 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 02/09/2024 11:40 to 02/09/2024 14:40
Amount: 18 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118066MARKET INTERVENTION02/09/2024 04:31:32 PM

Cancellation - AEMO Intervention Event - SA region 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 26/09/2024

Refer to Market Notice 117813

The AEMO Intervention Event and all associated directions are cancelled from 1630 hrs on 02/09/2024.



Manager NEM Real Time Operations
     
118065RECLASSIFY CONTINGENCY02/09/2024 02:24:06 PM

Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Cancellation time: 02/09/2024 14:24

Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Refer AEMO Electricity Market Notice 118055

Auto-generated on behalf of Manager NEM Real Time Operations
     