Market Notices

118587RECLASSIFY CONTINGENCY03/10/2024 12:11:42 PM

Cancellation of Reclassification of a Non-Credible Contingency Event: Glenrowan No1 66kV Bus- Vic region - 18/06/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Reclassification of a Non-Credible Contingency Event: Glenrowan No1 66kV Bus- Vic region - 18/06/2024.

Refer AEMO Electricity Market Notice 117043

Based on advice from the asset owner, AEMO considers the trip of the following element is no longer reasonably possible. Accordingly its classification has reverted to a non-credible contingency event.


Region: Vic

Equipment: Glenrowan No1 66kV Bus

Cancellation time: 1215 hrs 03/10/2024

Constraint set(s) revoked: Nil


Manager NEM Real Time Operations
     
118586NON-CONFORMANCE03/10/2024 12:05:22 PM

NON-CONFORMANCE Region QLD1 Thursday, 3 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 3 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 03/10/2024 08:35 to 03/10/2024 12:05
Amount: -53 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
118584PRICES UNCHANGED03/10/2024 10:36:15 AM

[EventId:202410031010_confirmed] Prices for interval 03-Oct-2024 10:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 3 October 2024

PRICES ARE NOW CONFIRMED for trading interval 03-Oct-2024 10:10.

In accordance with Market Notice 118574 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118583PRICES UNCHANGED03/10/2024 10:35:03 AM

[EventId:202410031030_confirmed] Prices for interval 03-Oct-2024 10:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 3 October 2024

PRICES ARE NOW CONFIRMED for trading interval 03-Oct-2024 10:30.

In accordance with Market Notice 118578 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118582PRICES UNCHANGED03/10/2024 10:33:57 AM

[EventId:202410031025_confirmed] Prices for interval 03-Oct-2024 10:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 3 October 2024

PRICES ARE NOW CONFIRMED for trading interval 03-Oct-2024 10:25.

In accordance with Market Notice 118577 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118581PRICES UNCHANGED03/10/2024 10:32:48 AM

[EventId:202410031020_confirmed] Prices for interval 03-Oct-2024 10:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 3 October 2024

PRICES ARE NOW CONFIRMED for trading interval 03-Oct-2024 10:20.

In accordance with Market Notice 118576 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118580PRICES UNCHANGED03/10/2024 10:30:21 AM

[EventId:202410031015_confirmed] Prices for interval 03-Oct-2024 10:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 3 October 2024

PRICES ARE NOW CONFIRMED for trading interval 03-Oct-2024 10:15.

In accordance with Market Notice 118575 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118579PRICES UNCHANGED03/10/2024 10:31:41 AM

[EventId:202410031005_confirmed] Prices for interval 03-Oct-2024 10:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 3 October 2024

PRICES ARE NOW CONFIRMED for trading interval 03-Oct-2024 10:05.

In accordance with Market Notice 118572 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118569RECLASSIFY CONTINGENCY02/10/2024 07:42:34 PM

Cancellation: Reclassification of a Non-Credible Contingency Event: Biloela -Biloela Tee 7110/2 132kV line and Biloela -Biloela Tee 7109/2 132kV line in QLD due to Other Threats.

AEMO ELECTRICITY MARKET NOTICE.
AEMO considers the occurrence of a non-credible contingency event due to other threats advised in AEMO Electricity Market Notice 118563 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 1930 hrs 02/10/2024.

Manager NEM Real Time Operations
     