PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120973 is cancelled at 0845 hrs 27/11/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120974 has been updated at 0730 hrs to the following:
[1.] From 1400 hrs 27/11/2024 to 1530 hrs 27/11/2024.
The forecast capacity reserve requirement is 820 MW.
The minimum capacity reserve available is 82 MW.
[2.] From 1700 hrs 27/11/2024 to 1900 hrs 27/11/2024.
The forecast capacity reserve requirement is 800 MW.
The minimum capacity reserve available is 50 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 84 MW at approximately 1530 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 27/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120975 has been updated at 0115 hrs to the following:
[1.] From 1400 hrs 27/11/2024 to 1430 hrs 27/11/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 1052 MW.
[2.] From 1900 hrs 27/11/2024 to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 973 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120989 has been updated at 0100 hrs 27/11/2024 to the following:
[2.] From 0830 hrs 29/11/2024 to 1130 hrs 29/11/2024.
The forecast capacity reserve requirement is 1650 MW.
The minimum capacity reserve available is 1467 MW.
[3.] From 1330 hrs 29/11/2024 to 1900 hrs 29/11/2024.
The forecast capacity reserve requirement is 1487 MW.
The minimum capacity reserve available is 700 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120988 has been updated at 0100 hrs 27/11/2024 to the following:
[1.] From 1200 hrs 28/11/2024 to 2130 hrs 28/11/2024.
The forecast capacity reserve requirement is 1367 MW.
The minimum capacity reserve available is 489 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period[s]:
[1.] From 1700 hrs 28/11/2024 to 1800 hrs 28/11/2024.
The forecast capacity reserve requirement is 776 MW.
The minimum capacity reserve available is 728 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Non-credible contingency event - NSW region - 26/11/2024
Non-credible contingency event - NSW region - 26/11/2024
At 1637 hrs Uranquinty Unit 12 tripped and at 1639 hrs Uranquinty Units 11 and 13 tripped.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120972 is cancelled at 16:50 hrs 26/11/2024.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations