Non-credible contingency event - QLD region - 12/12/2024
Non-credible contingency event - QLD region - 12/12/2024
At 2026 hrs the Kamerunga to Barron George 132 kV Line 7184 and the Kamerunga to Barron George 132 kV Line 7141 tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for NSW, SA, VIC from 12 Dec 2024 to 16 Dec 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
NSW
Yass (39+ Deg C): 16th Dec
SA
Adelaide West Terrace (39+ Deg C): 15th Dec
Clare High School (39+ Deg C): 15th Dec
Port Augusta Ap (39+ Deg C): 14th Dec, 15th Dec
VIC
Latrobe Valley Ap (39+ Deg C): 16th Dec
Melbourne Olympic Park (39+ Deg C): 16th Dec
Mildura Ap (39+ Deg C): 15th Dec, 16th Dec
Mortlake (39+ Deg C): 16th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Request for Generator Recall Information for the period 16/12/2024 and 17/12/2024 for Region NSW
Refer to AEMO Electricity Market Notice no. 121760, 121762, and 121765.
Please provide Generator Recall Information for the period from 16/12/2024 to 17/12/2024, by 1200 hrs on 13/12/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Request for Generator Recall Information for the period 16/12/2024 for Region VIC
Refer to AEMO Electricity Market Notice no. 121767.
Please provide Generator Recall Information for the period 16/12/2024, by 1200 hrs on 13/12/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
[EventId:202412120205_review] Prices for interval 12-Dec-2024 02:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 0200 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 02:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120200_review] Prices for interval 12-Dec-2024 02:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0155 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 02:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120155_review] Prices for interval 12-Dec-2024 01:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0150 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120150_review] Prices for interval 12-Dec-2024 01:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0145 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120145_review] Prices for interval 12-Dec-2024 01:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0140 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.