120889RESERVE NOTICE24/11/2024 06:17:52 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 24/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 24/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1541 MW
The minimum capacity reserve available is 1460 MW

Manager NEM Real Time Operations
     
120836INTER-REGIONAL TRANSFER22/11/2024 07:32:00 PM

Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024

At 1911 hrs 22/11/2024 there was an unplanned outage of the No.2 leg of Directlink.

The following constraint set(s) invoked at 1920 hrs 22/11/2024
N-X_MBTE_2

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
120835RESERVE NOTICE22/11/2024 06:41:52 PM

Cancellation of Actual (LOR1) condition in the NSW region - 22/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 22/11/2024

The Actual LOR1 Condition in the NSW region advised in AEMO Electricity Market Notice No.120833 is cancelled at 1838 hrs 22/11/2024.

Manager NEM Real Time Operations
     
120833RESERVE NOTICE22/11/2024 06:12:08 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 22/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 22/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.

The Actual LOR1 condition is forecast to exist until 1830 hrs.

The forecast capacity reserve requirement is 1396 MW.
The minimum capacity reserve available is 1348 MW.


Manager NEM Real Time Operations
     
120831INTER-REGIONAL TRANSFER22/11/2024 05:29:01 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 2 Leg of Directlink .

The following constraint set was invoked at 1720 hrs 22/11/2024

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
120800PRICE ADJUSTMENT22/11/2024 11:27:26 AM

[EventId:202411221115_confirmed] Prices for interval 22-Nov-2024 11:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1126 hrs on 22 November 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:15.

In accordance with Market Notice 120795 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs applied. Prices have been carried forward from the previous dispatch interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 $64.00 $25.81
QLD1 $62.79 $26.90
SA1 $8.61 $11.91
VIC1 $8.95 $12.00
LOWER1SEC
NSW1 $0.94 $0.10
QLD1 $0.94 $0.10
SA1 $0.94 $0.10
VIC1 $0.94 $0.10
LOWER60SEC
NSW1 $4.64 $1.82
QLD1 $4.64 $1.82
SA1 $4.64 $1.82
VIC1 $4.64 $1.82
LOWER6SEC
NSW1 $9.69 $4.89
QLD1 $9.69 $4.89
SA1 $9.69 $4.89
VIC1 $9.69 $4.89
LOWERREG
NSW1 $9.99 $19.85
QLD1 $9.99 $19.85
SA1 $9.99 $19.85
VIC1 $9.99 $19.85
RAISE1SEC
NSW1 $0.84 $0.05
QLD1 $0.84 $0.05
SA1 $0.84 $0.05
TAS1 $0.84 $0.05
VIC1 $0.84 $0.05
RAISE5MIN
NSW1 $0.05 $0.10
QLD1 $0.05 $0.10
SA1 $0.05 $0.10
VIC1 $0.05 $0.10
RAISE60SEC
NSW1 $0.00 $0.01
QLD1 $0.00 $0.01
SA1 $0.00 $0.01
VIC1 $0.00 $0.01
RAISE6SEC
NSW1 $0.01 $0.00
QLD1 $0.01 $0.00
SA1 $0.01 $0.00
VIC1 $0.01 $0.00
RAISEREG
NSW1 $7.99 $1.00
QLD1 $7.99 $1.00
SA1 $7.99 $1.00
VIC1 $7.99 $1.00


This is an AEMO autogenerated Market Notice.
     
120797PRICE ADJUSTMENT22/11/2024 11:17:32 AM

[EventId:202411221110_confirmed] Prices for interval 22-Nov-2024 11:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1117 hrs on 22 November 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:10.

In accordance with Market Notice 120794 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs applied. Prices have been carried forward from the previous dispatch interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 $150.01 $25.81
QLD1 $143.43 $26.90
SA1 $53.81 $11.91
VIC1 $55.02 $12.00
LOWER5MIN
NSW1 $1.57 $0.39
QLD1 $1.57 $0.39
SA1 $1.57 $0.39
VIC1 $1.57 $0.39
LOWER60SEC
NSW1 $4.64 $1.82
QLD1 $4.64 $1.82
SA1 $4.64 $1.82
VIC1 $4.64 $1.82
LOWER6SEC
NSW1 $9.69 $4.89
QLD1 $9.69 $4.89
SA1 $9.69 $4.89
VIC1 $9.69 $4.89
LOWERREG
NSW1 $20.90 $19.85
QLD1 $20.90 $19.85
SA1 $20.90 $19.85
VIC1 $20.90 $19.85
RAISE1SEC
NSW1 $0.10 $0.05
QLD1 $0.10 $0.05
SA1 $0.10 $0.05
TAS1 $0.10 $0.05
VIC1 $0.10 $0.05
RAISE5MIN
NSW1 $0.05 $0.10
QLD1 $0.05 $0.10
SA1 $0.05 $0.10
VIC1 $0.05 $0.10
RAISE60SEC
NSW1 $0.05 $0.01
QLD1 $0.05 $0.01
SA1 $0.05 $0.01
VIC1 $0.05 $0.01
RAISE6SEC
NSW1 $0.10 $0.00
QLD1 $0.10 $0.00
SA1 $0.10 $0.00
VIC1 $0.10 $0.00
RAISEREG
NSW1 $5.00 $1.00
QLD1 $5.00 $1.00
SA1 $5.00 $1.00
VIC1 $5.00 $1.00


This is an AEMO autogenerated Market Notice.
     
120724GENERAL NOTICE21/11/2024 12:37:48 PM

Network Augmentation Commissioned - QLD Region - 21/11/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 21/11/2024

Commissioned:

Belmont No.2 275 kV 150 MVar reactor

Manager NEM Real Time Operations
     
120706GENERAL NOTICE20/11/2024 11:00:44 AM

Project Energy Connect (PEC-1) testing 21st November 2024 0600-0900 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 120307

There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 21st November from 06:00hrs to 09:00hrs

This test includes includes a fast runback of Murraylink.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm