Filter by category
Filter by Date
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 3/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121407 has been updated at 1015 hrs to the following:
[1.] From 1330 hrs 03/12/2024 to 1500 hrs 03/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 461 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Duration: 03/12/2024 10:08 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 03/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:
[1.] From 1330 hrs 03/12/2024 to 1400 hrs 03/12/2024.
The forecast capacity reserve requirement is 771 MW.
The minimum capacity reserve available is 741 MW.
[2.] From 1430 hrs 03/12/2024 to 1500 hrs 03/12/2024.
The forecast capacity reserve requirement is 809 MW.
The minimum capacity reserve available is 636 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202412030705_review] Prices for interval 03-Dec-2024 07:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 0700 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 07:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412030700_review] Prices for interval 03-Dec-2024 07:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0655 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 07:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412030655_review] Prices for interval 03-Dec-2024 06:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0650 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 06:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412030650_review] Prices for interval 03-Dec-2024 06:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0645 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 06:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412030645_review] Prices for interval 03-Dec-2024 06:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0640 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 06:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412030640_review] Prices for interval 03-Dec-2024 06:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0635 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 06:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.