Filter by category
Filter by Date
[EventId:202411270945_review] Prices for interval 27-Nov-2024 09:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0940 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 09:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Palmerston - Hadspen 3 & 4 110kV and
Duration: 27/11/2024 09:15 until further notice
Constraint set(s) invoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1730 hrs 27/11/2024 to 1830 hrs 27/11/2024.
The forecast capacity reserve requirement is 1263 MW.
The minimum capacity reserve available is 919 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120973 is cancelled at 0845 hrs 27/11/2024.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV
Duration: 27/11/2024 08:30 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: VIC1
Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV
Cancellation time: 27/11/2024 04:34
Constraint set(s) revoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 121019
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC1
Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV
Duration: 27/11/2024 03:29 until further notice
Constraint set(s) invoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: VIC1
Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV
Cancellation time: 27/11/2024 03:24
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 121016
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 27/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120975 has been updated at 0115 hrs to the following:
[1.] From 1400 hrs 27/11/2024 to 1430 hrs 27/11/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 1052 MW.
[2.] From 1900 hrs 27/11/2024 to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 973 MW.
Manager NEM Real Time Operations