121128RESERVE NOTICE27/11/2024 08:03:50 PM

Cancellation of Actual (LOR1) condition in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 27/11/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121106 is cancelled at 2000 hrs 27/11/2024.

Manager NEM Real Time Operations
     
121106RESERVE NOTICE27/11/2024 04:50:52 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121089 has been updated at 1645 hrs to the following:

The Actual LOR1 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 859 MW.

Manager NEM Real Time Operations
     
121089RESERVE NOTICE27/11/2024 02:48:34 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1430 hrs.

The Actual LOR1 condition is forecast to exist until 1630 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 710 MW.

Manager NEM Real Time Operations
     
121082RECLASSIFY CONTINGENCY27/11/2024 01:30:20 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 27/11/2024 13:30 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
121073RECLASSIFY CONTINGENCY27/11/2024 01:13:31 PM

Reclassification of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Duration: 27/11/2024 13:13 until further notice

Constraint set(s) invoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
121058RECLASSIFY CONTINGENCY27/11/2024 11:34:15 AM

Cancellation of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV

Cancellation time: 27/11/2024 11:34

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 121027

Auto-generated on behalf of Manager NEM Real Time Operations
     
121052NON-CONFORMANCE27/11/2024 10:26:35 AM

NON-CONFORMANCE Region QLD1 Wednesday, 27 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 27 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 27/11/2024 09:45 to 27/11/2024 10:25
Amount: 36 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
121051NON-CONFORMANCE27/11/2024 10:25:35 AM

NON-CONFORMANCE Region QLD1 Wednesday, 27 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 27 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 27/11/2024 09:55 to 27/11/2024 10:25
Amount: -17 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121050RECLASSIFY CONTINGENCY27/11/2024 10:19:16 AM

Cancellation of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Cancellation time: 27/11/2024 10:19

Constraint set(s) revoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 121030

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm