121147INTER-REGIONAL TRANSFER28/11/2024 12:32:16 PM

Cancellation - Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

Refer AEMO Electricity Market Notice 121142

Constraint set I-QN_1000 was invoked from 0955 hrs until 1230 hrs 28/11/2024.

This constraint set contains equations with the following interconnector on the LHS;

NSW1-QLD1

Manager NEM Real Time Operations
     
121142INTER-REGIONAL TRANSFER28/11/2024 10:02:47 AM

Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked the following constraint set I-QN_1000 from 0955 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

NSW1-QLD1

Manager NEM Real Time Operations
     
121128RESERVE NOTICE27/11/2024 08:03:50 PM

Cancellation of Actual (LOR1) condition in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 27/11/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121106 is cancelled at 2000 hrs 27/11/2024.

Manager NEM Real Time Operations
     
121106RESERVE NOTICE27/11/2024 04:50:52 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121089 has been updated at 1645 hrs to the following:

The Actual LOR1 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 859 MW.

Manager NEM Real Time Operations
     
121089RESERVE NOTICE27/11/2024 02:48:34 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1430 hrs.

The Actual LOR1 condition is forecast to exist until 1630 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 710 MW.

Manager NEM Real Time Operations
     
121011RESERVE NOTICE26/11/2024 08:29:09 PM

Cancellation of Actual (LOR1) condition in the NSW region - 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 26/11/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121009 is cancelled at 2015 hrs 26/11/2024.

Manager NEM Real Time Operations
     
121009RESERVE NOTICE26/11/2024 04:56:18 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 886 MW

Manager NEM Real Time Operations
     
121008POWER SYSTEM EVENTS26/11/2024 04:55:00 PM

Non-credible contingency event - NSW region - 26/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 26/11/2024

At 1637 hrs Uranquinty Unit 12 tripped and at 1639 hrs Uranquinty Units 11 and 13 tripped.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
120943MARKET SYSTEMS25/11/2024 05:22:50 PM

INC0138597 - RESOLVED - EMMS

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - SERVICE RESTORED

The Electricity Market Management System service has been restored.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm